Topic awaiting preservation: some math help please (Page 1 of 1) Pages that link to <a href="https://ozoneasylum.com/backlink?for=24982" title="Pages that link to Topic awaiting preservation: some math help please (Page 1 of 1)" rel="nofollow" >Topic awaiting preservation: some math help please <span class="small">(Page 1 of 1)</span>\

 
GRUMBLE
Paranoid (IV) Mad Scientist

From: Omicron Persei 8
Insane since: Oct 2000

posted posted 02-10-2005 18:17

i want to calculate the remaining time of a renderjob.
say i have 100 frames to render and 3 machines workin on that.
machine A takes 3 minutes per frame, machine B 2 minutes and machine C 1 minute.
they all start at the same time.
how can i calculate the time it takes for all 100 frames to complete?

thanks!



(Edited by GRUMBLE on 02-10-2005 18:17)

hyperbole
Paranoid (IV) Inmate

From: Madison, Indiana, USA
Insane since: Aug 2000

posted posted 02-10-2005 18:25

Machine A 3 min/frame = 1/3 frame/min
Machine B 2 min/frame = 1/2 frame/min
Machine C 1 min/frame = 1 frame.min


(1 fpm + .5 fpm + .333 fpm ) x Z min = 100 frames

Z = 100 / 1.8333
Z = 54.5 minutes





-- not necessarily stoned... just beautiful.


(Edited by hyperbole on 02-10-2005 18:27)

Ogie
Bipolar (III) Inmate

From: I come from the land down under.
Insane since: Nov 2001

posted posted 02-10-2005 18:25

just out of quick caculation you will be rendering 5 1/2 frames every three minutes, which means it will take you 54.55 minutes to render 100 frames

GRUMBLE
Paranoid (IV) Mad Scientist

From: Omicron Persei 8
Insane since: Oct 2000

posted posted 02-10-2005 18:54

thanks!

Archem
Neurotic (0) Inmate
Newly admitted

From:
Insane since: Feb 2005

posted posted 02-11-2005 23:36

It'll actually take 55 minutes. 5.5 frames in three minutes 18 times over. gives you 99 frames rendered. The last fram still takes a full minute on the fastest computer.